FONTAINE + DIMEO — CONCEPTUAL ESTIMATING DASHBOARD

Pollard Middle School — Layered Cost Estimate

Structured per Mark Abdella's MSBA framework: Base scope (MSBA guidelines) → community add-ons → site → renewables → MBTA → CM fees. Every line shows MSBA reimbursability and flags assumptions vs. verified benchmarks.

Verified — benchmark data sourced
MSBA reimbursable
Not reimbursable
TOTAL PROJECT COST
$258M
All-in budget — 6 categories
EST. MSBA REIMBURSEMENT
$95–110M
~40-43% of eligible costs
EST. COST TO NEEDHAM
$148–163M
After MSBA reimbursement
BUILDING SIZE
~250K SF
Ph1: 175K + Ph2: 75K

1. Base Middle School Scope — MSBA Space Guidelines

$155–170M
LINE ITEM
ESTIMATED COST
$/SF
MSBA
Structural / Foundations / Superstructure
Steel, concrete, metal deck — both phases
Source: Walpole $6.15M steel + Peck $5.5M steel, scaled to 250K SF
$32–36M
$128–144
Reimb
Building Envelope
Exterior walls, curtain wall, windows, roofing, waterproofing, insulation
Source: Walpole $3.8M openings + $2.0M roof; Peck $2.42M insul + $2.05M openings, scaled
$22–26M
$88–104
Reimb
Interior Construction
Partitions, doors, finishes, ceilings, flooring — classrooms, corridors, admin
Source: Walpole $10.54M finishes + $1.66M casework; Peck $5.81M finishes, scaled
$26–30M
$104–120
Reimb
Mechanical / HVAC (Base Building)
Air handling, distribution, controls, BAS — excludes geothermal heat source
Source: Walpole $8.67M HVAC for 162K SF; Peck $4.78M + $1.16M controls, scaled
$20–24M
$80–96
Reimb
Electrical
Power distribution, lighting, fire alarm, low voltage, data
Source: Walpole $11.49M for 162K SF; Peck $4.21M + $1.76M comms + $1.02M security, scaled
$16–19M
$64–76
Reimb
Plumbing & Fire Protection
Domestic water, waste, fixtures, sprinkler system
Source: Walpole $4.39M plumb + $1.03M FP; Peck $2.09M plumb + $1.13M FP, scaled
$9–11M
$36–44
Reimb
Elevator(s)
Permanent building elevator(s) — ADA compliance
Source: Walpole $387K; Peck $125K
$400–600K
Reimb
Kitchen / Food Service Equipment
Commercial kitchen, serving lines, walk-in coolers, cafeteria
Source: Walpole $1.18M for 162K SF, scaled
$2.5–3.5M
Reimb
Gymnasium
Gym structure, flooring, bleachers, scoreboard, MEP
$5–6M
Reimb
Technology & AV Infrastructure
Classroom AV, network backbone, wireless, security cameras
$4–5M
$16–20
Reimb
Furnishings, Fixtures & Equipment (FF&E)
Classroom furniture, lab casework, signage
Source: Peck $927K furnishings; Walpole $1.66M casework, scaled
$5–6M
$20–24
Partial
Concrete (Foundations, SOG, Slabs)
Cast-in-place foundations, slab on grade, elevated slabs
Source: Walpole $4.59M; Peck $5.95M, scaled to 250K SF
$8–10M
$32–40
Reimb
Masonry
CMU backup, brick veneer, stone accents
Source: Walpole $2.94M; Peck $5.58M, scaled
$5–7M
$20–28
Reimb
Subtotal — Base Middle School
$155–170M
$620–680/SF
Reimb

2. Specialty Program Spaces — Community Add-Ons / Auditorium

$14–18M
LINE ITEM
ESTIMATED COST
$/SF
MSBA
750-Seat Performing Arts Auditorium — Interior Fit-Out
Benchmarked from Shane Sampson 600-seat data, scaled to 750 seats. Ref sizes: E.Longmeadow 7,800 SF, Agawam 8,030 SF, Doherty 9,300 SF
Wall Framing
Interior wall framing for auditorium
Source: Shane Sampson benchmark
$144K
Not Reimb
Stage Framing
Stage structural framing
Source: Shane Sampson benchmark
$44K
Not Reimb
Platform / Sloped Seating Construction
Raked seating platform structure
Source: Shane Sampson benchmark
$100K
Not Reimb
Stage Wood Flooring
Hardwood stage deck
Source: Shane Sampson benchmark
$51K
Not Reimb
Doors
Auditorium entry and exit doors
Source: Shane Sampson benchmark
$18.5K
Not Reimb
Room Flooring (Carpet)
House seating area carpet
Source: Shane Sampson benchmark
$42.5K
Not Reimb
Acoustical Wall Finishes
Specialty acoustic wall panels and treatments
Source: Shane Sampson benchmark
$287.5K
Not Reimb
Ceiling Acoustics
Acoustical ceiling systems and baffles
Source: Shane Sampson benchmark
$180.9K
Not Reimb
Signage
Interior auditorium signage
Source: Shane Sampson benchmark
$10K
Not Reimb
Fixed Seating — 750 Seats
750 seats × $475/seat (scaled from 600-seat benchmark @ $475/seat = $285K)
Source: Shane Sampson benchmark, scaled
$356.3K
$475/seat
Not Reimb
Lighting Package
Theatrical / performance lighting system
Source: Shane Sampson benchmark
$425K
Not Reimb
AV Package
Audio, video, projection, control room equipment
Source: Shane Sampson benchmark
$775K
Not Reimb
Curtains & Rigging
Stage curtains, tracks, rigging systems
Source: Shane Sampson benchmark
$125K
Not Reimb
Catwalk & Railings
Technical catwalk, safety railings, access systems
Source: Shane Sampson benchmark
$300K
Not Reimb
Auditorium Interior Subtotal (excl. structure/envelope)
$2,860K
Not Reimb
Auditorium Structure & Envelope
Shell, fly loft, structural steel, foundations, exterior walls (not in Shane Sampson interior benchmark)
$6–8M
Not Reimb
Auditorium MEP
HVAC, electrical, plumbing, fire protection for auditorium volume (not in interior benchmark)
$2–3M
Not Reimb
Other Community Enhancements
Extended lobby, community meeting spaces, enhanced athletic facilities
$1–1.5M
Partial
Subtotal — Community Add-Ons / Auditorium
$14–18M
Mostly Not

3. Site Development Costs

$23–28M
LINE ITEM
ESTIMATED COST
QUANTITY
MSBA
Demolition & Abatement — Existing Pollard Building
Phase 2 — complete demo of existing school, hazmat abatement, haul-off
Source: Walpole $2.44M demo/abatement for 162K SF, scaled
$3.5–4.5M
~120K SF
Reimb
Earthwork — Phase 1 Mass Excavation
Mass excavation, lower level @ el. 130, upper @ el. 160
Source: Walpole $9.95M earthwork for 162K SF, scaled
$4–5M
~50,000 CY
Reimb
Earthwork — Phase 2
Grade 6 Academy wing, remaining sitework
$1–1.5M
~13,000 CY
Reimb
Support of Excavation (SOE)
Sheeting, shoring, soldier piles — grade differential
$2.5–3.5M
Reimb
Retaining Walls
Permanent retaining structures, grade changes
$2–3M
Reimb
Soil Export & Backfill
25-30K CY excess soil export + structural backfill
$2.5–3.5M
25-30K CY out
Reimb
Site Utilities
Water, sewer, storm, electric, gas, data — new connections
Source: Peck $1.28M utilities, scaled
$2.5–3.5M
Reimb
Parking, Roadways, Walkways
Permanent parking, bus loop, drop-off, sidewalks, curbing
$2–2.5M
Reimb
Landscaping & Athletic Fields
Finish grading, Warner Field restoration, plantings, irrigation
Source: Walpole $1.55M exterior/landscaping, scaled
$1.5–2M
Partial
Stormwater Management
Detention/infiltration, sediment basins, SWPPP, EPA NPDES
$1.5–2M
Reimb
Subtotal — Site Development
$23–28M
Mostly Reimb

4. Renewable Energy — Solar & Geothermal

$12–16M
LINE ITEM
ESTIMATED COST
QUANTITY
MSBA
Geothermal System — Verified from Agawam HS Actuals
Agawam: 149 boreholes, 510 LF each, 160 LF casing each. Total vertical LF: 75,990. Cost/well: $30,705
Geothermal Drilling Operation
Borehole drilling — ~149 wells × 510 LF each (Pollard may differ in count based on load calcs)
Source: Agawam HS actuals — $3.3M
$3.3M
149 wells
Green Incentive
Lateral Piping
28,000 LF of lateral piping from boreholes to vault/headers
Source: Agawam HS actuals — $825K
$825K
28,000 LF
Green Incentive
Grout
Borehole grouting — thermal conductivity grout
Source: Agawam HS actuals — $250K
$250K
Green Incentive
Vertical Loops
U-bend loop assemblies installed in boreholes
Source: Agawam HS actuals — $150K
$150K
Green Incentive
Testing & Flushing
System testing, flow balancing, flushing
Source: Agawam HS actuals — $50K
$50K
Green Incentive
Geothermal Field Subtotal
$4,575K
Green $
Water-Source Heat Pumps
5 × 129-ton WSHP units @ $231K each
Source: Agawam HS actuals — $1,155K
$1,155K
5 units
Green Incentive
Mechanical Room Piping
Header piping, pumps, valves, mechanical room fit-out
Source: Agawam HS actuals — $250-300K
$250–300K
Green Incentive
Geothermal + Heat Pumps Total (Agawam Verified)
~$6.0M
Green $
Pollard-Specific Geothermal Adjustments
MBTA tunnel crossing, additional laterals, field configuration differences from Agawam, contingency
$2–4M
Green Incentive
Solar / Photovoltaic Arrays
Rooftop or parking canopy PV — Net Zero readiness
$3–5M
Green Incentive
Subtotal — Renewables
$12–16M
Green $

5. MBTA — Rail Adjacency Costs

$2–4M
LINE ITEM
ESTIMATED COST
NOTES
MSBA
Flagging & Inspector Services
Required for all work within fouling distance of tracks — at contractor expense
$600K–1.2M
Multi-year
Unclear
MBTA Insurance (RPLI)
Railroad Protective Liability — $5M/$10M required within 50ft of track
$250–500K
Unclear
MBTA Licenses, Easements, Deposits
License for entry, advance deposits, legal/admin fees
$250–500K
Unclear
Rail-Interface Construction Measures
Protection fencing, vibration monitoring, track protection, tunnel work for geothermal
$600K–1.2M
Unclear
Police Details & Security
Required for traffic control/security near active rail
$150–300K
Unclear
Subtotal — MBTA
$2–4M
TBD

6. CM Fee, General Conditions, Gen Requirements & Insurance

$25–30M
LINE ITEM
ESTIMATED COST
% OF BUDGET
MSBA
General Conditions
Project staff, field office, temp facilities, equipment, utilities, dumpsters, progress cleaning
Source: Walpole $6.97M GRs/GCs for $95M project; Peck $2.2M GRs for $58.8M, scaled
$13–15M
~5-6%
Reimb
General Requirements
Permits, testing, commissioning, closeout, surveys
$5–6M
~2%
Reimb
CM Fee
Construction management fee — percentage of construction cost
Source: Walpole $1.85M CM Fee for $95M project (~2%), scaled
$4.5–5.5M
~2%
Reimb
Insurance & Bond
Builders risk, GL, performance/payment bond — based on total construction value
Source: Walpole $1.5M insurance/bond for $95M, scaled
$2.5–3.5M
~1%
Reimb
Subtotal — CM/GC/Insurance
$25–30M
~10-12%
Reimb

TOTAL PROJECT COST — ALL 6 LAYERS

$258,000,000

Cost to Needham — After MSBA Reimbursement

This is the "checking account" view — what does each decision actually cost the Town after MSBA's share? Every project decision should be evaluated through this lens. Total budget: $258M.
MSBA ~$95–110M
Town Share ~$110–125M
100% Town ~$23–38M
MSBA Reimbursement
~$95–110M
Town Share of Reimbursable
~$110–125M
Non-Reimbursable (100% Town)
~$23–38M
NOT REIMBURSABLE — 100% TOWN COST
• 750-seat auditorium (all-in): $12–16.5M
• Community enhancements: $1–1.5M
• Portions of MBTA costs: $2–4M (TBD)
• Portions of renewables: TBD — Green incentive
KEY REIMBURSABLE DECISIONS
• Extended gen conditions (longer schedule) = reimbursable
• Site development / earthwork = reimbursable
• Base building MEP/structure = reimbursable
• Geothermal = Green School incentive
• CM fee + insurance = reimbursable